Audit: Costs, Delays Build for Boeing’s NASA Rocket, Capsule

Audit: Costs, Delays Build for Boeing’s NASA Rocket, Capsule

June 19, 2019, 11:16 PM

NASA’s flagship space launch system being built by Boeing is taking years longer than expected with cost overruns of nearly $2 billion, an audit found Wednesday, raising questions about meeting a goal of returning humans to the moon by 2024.

The General Accounting Office (GAO) identified $1.8 billion in cost overruns, including $800 million that NASA obscured in previous reports on its Space Launch System (SLS), the rocket and capsule that will eventually take humans back to the moon.

The issues around the rocket’s development, led by Boeing Co, mean that the first launch of the SLS originally scheduled for late 2017 could be delayed until June 2021.

Boeing’s space division restructured the SLS leadership team in 2018 and early 2019 to adjust to the program challenges and simplified its manufacturing process, Boeing spokesman Jerry Drelling said.

“No one is building a rocket like this, and we’re creating a very in-depth database for all future rockets,” he said.

The Trump administration directed NASA in March to land humans on the lunar surface by 2024, part of a broader program called Artemis that will use the moon as a staging ground for eventual missions to Mars.

The accelerated timeline, four years faster than originally planned, is likely to cost $20 billion to $30 billion over the next five years, NASA Administrator Jim Bridenstine said in an interview with CNN last week.

Shifting costs

The $1.8 billion cost overrun was nearly double what NASA reported to its inspector general in 2018 for SLS and the Orion capsule — the crew pod built by Lockheed Martin that will launch atop the rocket — the report said.

“NASA’s reporting of cost data for the SLS and Orion programs is not fully transparent,” it said.

NASA obscured the full cost growth of the SLS program by shifting roughly $800 million to future SLS missions to downplay the cost of the initial mission, the GAO report said.

Officials from NASA and Boeing also underestimated the manufacturing complexity of the “core stage” of four attached rocket engines, which could increase the cost and cause delays of two years or more, the report said.

Cost overruns, award fees

Despite the cost overruns, NASA has awarded Boeing at least $146 million and Lockheed $87 million in “award fees” to stay on schedule, but “the programs have not always achieved overall desired outcomes,” the report said. The space agency agreed to the report’s recommendation to re-evaluate its incentive system.

NASA’s associate administrator for human spaceflight and operations, William Gerstenmaier, said in a response to the GAO’s report that the audit “does not acknowledge NASA is constructing some of the most sophisticated hardware ever built.” A NASA spokeswoman declined further comment.

Original Article

CATCH THE LATEST AMERICA'S VOICE LIVE SHOW

WATCH THE LATEST EDITION OF WAR ROOM WITH STEVE BANNON

CATCH THE AMERICAN SUNRISE SHOW M-F AT 8AM ET.

CATCH THE LATEST STEVE GRUBER SHOW

WATCH THE LATEST COWBOY LOGIC BARN PARTY SHOW

CATCH THE LATEST BREAKING POINT SHOW WITH DAVID ZERE

WATCH THE LATEST EDITION OF SECURING AMERICA WITH FRANK GAFFNEY

WATCH RAV'S SPECIAL REPORT M-5 AT 4PM ET.

WATCH RAV'S ELECTION NIGHT 2024 LIVE COVERAGE

WATCH ON RUMBLE WATCH ON GETTR

JOIN US IN LIVE CHAT 24/7 ON RUMBLE

JOIN US ON OUR 24/7 LIVE RUMBLE STREAM